OASIS / FUNDING

Where the funding goes.

Proceeds from the OASIS token pay for the work below, in order: a better model, a bench rig that tests it, then a full-scale pilot. These are estimated ranges, not quotes — each one is replaced with real numbers as we get them.

Three phasesEstimated total $768k – $2.06MUSD · EUR benchmarks converted at ~1.10
00Summary

Phases run in order and only as far as funding and partners allow. Nothing here is a promise of delivery, a return, or a price — it is what the work costs, as best we can estimate it today.

01Phase 01 · ModelIn progress

Take OASIS-0.1 from a steady-state estimate to an hour-by-hour model that an outside engineer has checked.

What it delivers

  • OASIS-0.2: full-year (8,760-hour) simulation against real weather files
  • An independent review of the model by a thermal engineering firm, published as-is
  • Every research note and model change logged publicly
ExpenseEstimated costBasis
Modelling engineer~4–6 months, hourly simulation and validation$40k – $80kOur estimate
Independent model reviewThird-party thermal engineering review$15k – $40kOur estimate
Weather and site dataTypical-year weather files, climate datasets$5k – $15kOur estimate
Phase 01 total$60k – $135k
02Phase 02 · Bench rigNext

Build a ~50 kW thermal test rig so the model is checked against measurements, not just itself.

What it delivers

  • A working capture → buffer → reject loop at bench scale
  • Measured data published next to the model’s predictions, including where they disagree
ExpenseEstimated costBasis
Load bank~50 kW liquid heater standing in for GPU racks$15k – $35kOur estimate
Heat exchanger, pumps, pipingPlate heat exchanger and the loop around it$10k – $25kOur estimate
Buffer tank~2 m³ insulated water tank$5k – $15kOur estimate
Dry cooler~60 kW$8k – $20kOur estimate
Sensors and controlsTemperature, flow and power metering; data logging$15k – $30kOur estimate
Lab space and integration~6 months of space and build labour$40k – $90kOur estimate
Phase 02 total$93k – $215k
03Phase 03 · 1 MW pilotLater

Retrofit one full-scale module onto a partner site’s existing cooling loop and run it for a year.

What it delivers

  • The first measured — not modeled — water and energy figures for System 001
  • A full cost breakdown from real quotes, replacing the estimates on this page
ExpenseEstimated costBasis
Heat exchanger skid~1 MW thermal, with isolation valves and bypass$60k – $150kOur estimate
Thermal buffer~2 MWh hot-water tankLarge district-heating tanks run ~€1–10/kWh; a tank this small costs more per kWh.$25k – $80kOur estimate
Recovery heat pump~400 kW thermal, lifting recovered heat to useful temperaturesIndustrial heat pumps: ~€300–1,000 per kW thermal, average ~€400.$130k – $440kPublished benchmark
Dry cooler~1.2 MW, sized with headroom$100k – $250kOur estimate
Controls and monitoringThe control layer, metering, data pipeline$40k – $90kOur estimate
InstallationPiping, electrical, structural — typically 0.5–1× equipment$180k – $500kOur estimate
Engineering and commissioningDesign, permits, partner integration, start-up$80k – $200kOur estimate
Phase 03 total$615k – $1.71M
04How these numbers are made

Published benchmark means the range comes from public cost data for that kind of equipment, scaled to the size listed. Our estimate means we have no public figure we trust yet; the range is our best judgement and will be replaced by vendor quotes. Installation and engineering are the least certain lines and are deliberately wide.

Sources